Sykesville · Planning Commission · Application

Enclave at Parkside - Preliminary Plan & Pattern Book

Application
Status
Approved
Filed
Apr 7, 2025
Project
Meetings
Citations
Process progress

Planning Commission: PEC Three-Step

Checklist
Site Plan Submission
Staff Completeness Review
PC Hearing - Concept
PC Hearing - Preliminary
PC Hearing - Final
Conditions Tracking
Process diagram
graph TD
    site_plan_submission(["Site Plan Submission"])
    staff_completeness["Staff Completeness Review"]
    concept["PC Hearing - Concept"]
    preliminary["PC Hearing - Preliminary"]
    final["PC Hearing - Final"]
    preliminary_conditions["Conditions Tracking"]
    DONE(("Done"))
    site_plan_submission -->|"Submitted"| staff_completeness
    staff_completeness -->|"Complete"| concept
    staff_completeness -->|"Incomplete"| site_plan_submission
    concept -->|"Approved"| preliminary
    concept -->|"Denied / Resubmit"| site_plan_submission
    preliminary -->|"Approved"| final
    preliminary -->|"Approved With Conditions"| preliminary_conditions
    preliminary -->|"Denied"| DONE
    preliminary_conditions -->|"Conditions Met"| final
    final -->|"Approved"| DONE
    final -->|"Denied"| DONE
    class site_plan_submission,staff_completeness,concept,preliminary,final,preliminary_conditions,DONE completedNode
    classDef completedNode fill:#dcfce7,stroke:#15803d,color:#15803d

Timeline

  • Apr 7, 2025
    MeetingPC meeting
    Consider/Discuss/Act on Enclave and Parkside Preliminary Plan and Pattern Book Review and Approval
  • Oct 7, 2024
    MeetingPC meeting
    Enclave and Parkside Development Updates
  • Feb 5, 2024
    MeetingPC meeting
    Enclave at Parkside - Close Public Hearing and Preliminay Plan Update
  • Aug 7, 2023
    MeetingPC meeting
    Public Hearing - The Enclave at Parkside Preliminary Plan and Pattern Book
  • Jul 5, 2023
    MeetingPC meeting
    The Enclave at Parkside Preliminary Plan Presentation

Citations

§180-142 Bulk regulations (lot area, lot width, and yard
The plan remains consistent with all bulk regulations approved during the concept plan stage.
§180-139 Required percenta’ e of land uses
The plan remains consistent with all land use percentages approved during the concept plan stage.
§180-143 Pattern book
A pattern book shall be submitted and approved as part of the preliminary plan phase.
§180-144 Approval process
Three-step approval process: concept, preliminary, final.

Project

Warfield
May 24, 2026